RE: Pathway Redevelopment


Due to the rain and losing power on the 22.10.12 the pathway redevelopment has been further delayed and work is unable to commence until all surfaces are 100% dry.

The rain has caused discolouration under the clear coat of the surface which now has to be grinded back and resurfaced.

 we appreciate your patience in regards to this and further details will be updated.

Please note that due to fine concrete dust we are unable to open the gym until further notice.  Under the manufacturer warranty we are unable to use the equipment during this time as it will wear down machinery and is against operational guidelines.

If you have any further questions please don’t hesitate to email us at: 

Photos Ref:


Kind Regards,

Cathedral Place Caretaking on behalf of Cathedral Place Body Corporate